Updates on the progress of the construction of the Audenreid AMD Treatment System in the Catawissa Creek Watershed.

Friday, October 28, 2005

The limestone is delivered and placed in tanks. Outlet pipes are being installed now.

 
 Posted by Picasa

After the recent rain, the elevated water levels are visible at the discharge.

 
 Posted by Picasa

The siphons are being installed.

 
 Posted by Picasa

Friday, October 21, 2005

The pipes were run under the gas line (with supervision from Sun Pipeline)

 
 Posted by Picasa

The siphons are being installed.

 
 Posted by Picasa

The gate valves for the tank inlet pipes have been installed.

 
 Posted by Picasa

The Three tanks are nearly filled.

 
 Posted by Picasa

Monday, October 10, 2005

The site has weathered the storm

Posted by Picasa

Valves at distribution tank

Posted by Picasa

Additional picture of valves

Posted by Picasa

Valve

Posted by Picasa

Valves have been installed

Posted by Picasa

Tanks are 75% full

Posted by Picasa