Audenreid

Updates on the progress of the construction of the Audenreid AMD Treatment System in the Catawissa Creek Watershed.

Tuesday, August 30, 2005


On September 7th, the SCD will be hosting a tour of the AUdenreid site. Come see the progress that has been made to date. The tour will be at 1:00pm. If you would like to go or need directions, please contact the Schuylkill Conservation District at (570) 622 3742 ext 120.

Backfilling the lines

Posted by Picasa

The pipes start to get connected to the tanks.

Posted by Picasa

A Picture of the three 18" lines coming from the discharge.

Posted by Picasa

Tanks 1 and 2 are being backfilled.

Posted by Picasa

A view of the intake system frombehind the tunnel.

Posted by Picasa

After the intake system has been installed.

Posted by Picasa

Another view of the tunnel before the intake system was installed.

Posted by Picasa

The distribution box has been installed.

Posted by Picasa

The siphons have arrived (Impressive)!

Posted by Picasa

As of now, all three tanks have been poured.

Posted by Picasa

The discharge was buried to prevent soil and other materials from getting into the treatment system.

Posted by Picasa

The concrete tanks are 120 ft. in diameter and 12 ft. deep.

Posted by Picasa

The tunnel, once daylighted, was an impressive site to see...It can only be seen in pictures now.

Posted by Picasa

All three tank floors were poured consecutively..The tank walls were constructed and poured one at a time.

Posted by Picasa

The discharge was daylighted for the 1st time in more than a decade.

Posted by Picasa

The pads for the tanks were quickly prepared as soon as excavation was completed. The site had a lot of water so the contractor had to do a lot of extra work to install adequate drainage.

Posted by Picasa

One large hold was excavated for the three tanks. This took several weeks to complete.

Posted by Picasa

Road was moved to make room for the concrete tanks. Additional stormwater management facilities had to be installed to handle upslope runoff.

Posted by Picasa

Construction just starting-Site has been cleared

Posted by Picasa

Pouring Concrete

Posted by Picasa

Welcome to the Audenreid Blog

I wanted to find a way to keep everyone updated on the Audenreid project and share pictures on the construction progress. I hope that this blog will serve that purpose. Come back often and check for updates on the system's progress. I will be posting photos regularly.

Thanks
Tom


Website Counters